Every bed in the optimal order from tools/plan_schedule.py, drawn on a 24-hour clock. The green bands are when someone is around to clear the bed. White space outside them is a finished print waiting for a person. Hover over a bed for its parts. The same data, with the trade-offs, is in schedule the print beds.

The workday plan puts the two longest LW-PLA beds in the daytime stretch and the 5 to 8 hour beds overnight. That is why it takes less than a day longer than being home all day. For the Survey3 build, beds g03 and g12 swap for their Survey3 versions, and the order and totals do not change.